  1. #8401
    Becoming a C2E Power Poster
    Join Date
    Jul 2015
    Location
    Vancouver - Edmonton
    Posts
    156

    Default

    Macewan Station is already built to accommodate 5 car trains and the platform width is 9m which is what every other station is built to. The part of the station that has a capacity of 100 is the small pedestrian bridge across the track, and as long as people continue down the stairs and fill up the platform below it really shouldn't be an issue. You can also walk west 100m and come into the station by way of the intersection at 105 and 105 and avoid that bottleneck altogether.

  2. #8402
    I'd rather C2E than work!
    Join Date
    May 2008
    Location
    Clareview
    Posts
    7,101

    Default

    It seems Belvedere is longer then the rest on the Capital line because of the long platform
    Mom said I should not talk to cretins!

  3. #8403

    Default

    Quote Originally Posted by realkevbo View Post
    Macewan Station is already built to accommodate 5 car trains and the platform width is 9m which is what every other station is built to. The part of the station that has a capacity of 100 is the small pedestrian bridge across the track, and as long as people continue down the stairs and fill up the platform below it really shouldn't be an issue. You can also walk west 100m and come into the station by way of the intersection at 105 and 105 and avoid that bottleneck altogether.
    And another reason for bottlenecks at macewan station is frequency of trains. At Coliseum, they could push one train after another. Here, they can only do every 10-15 minutes due to the signalling issue.

  4. #8404

    Default

    Quote Originally Posted by realkevbo View Post
    The part of the station that has a capacity of 100 is the small pedestrian bridge across the track, and as long as people continue down the stairs and fill up the platform below it really shouldn't be an issue.
    Thanks for the detailed response. That doesn't sound too difficult to upgrade. Does ETS or the city have any plans to improve the bottleneck?

Page 85 of 85 FirstFirst ... 35758182838485

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •